Friday, September 29, 2006

Sheppard Leslie update

Stage 2 is approaching completion. The switch to Stage 3 of the intersection work is scheduled for Monday Oct. 2, 2006 weather permitting. Upon completion of the Stage 3 setup, north/south pedestrian crossings will be provided for on the west side of the intersection only - no crossing on the east side of the intersection will be permitted for safety reasons. This is the reverse situation to Stage 1.

All the girders are in place for the new bridge at the Hospital and the contractor is working on completing the abutment wingwalls and parapet walls.