Leslie - Sheppard Construction Update
This update from Transportation Services was received in our office on August 1st and we just wanted to share it with you.
Councillors, this is to inform that tomorrow evening starting at 7 PM the contractor will be implementing the Stage 2 traffic control setup for the intersection work. Completion is scheduled for 6AM the next morning. Additional grinding of any pavement markings is scheduled for the next evening/night also. The work zone will be in the middle of the intersection with the traffic being maintained on all 4 sides. Pedestrians will be able to cross all 4 legs of the intersection. Technical Services and Transportation Services will be monitoring the new setup and making any adjustments as required.
By this week's end, the substructure(abutments and columns) for the new bridge at the Hospital should be complete. The box girders are tentatively scheduled to be erected around the third week of August.