Update: Leslie/ Sheppard Construction

Here is an update from a Senior Project Engineer that is working on the Leslie/Sheppard construction:

The road modifications at the Intersection are basically complete and paving and line marking is scheduled for the nights following the July 1 Long Weekend.

The Contractor will continue to widen Leslie St between Sheppard and Esther Shiner Boulevard. The west side work should be complete by the end of next week and the following week, the contractor will switchover to the east side of Leslie. Pedestrians will be maintained on 1 side of Leslie St. Currently the pedestrians are maintained on the east side. In about a week the pedestrians will be switched to the west side of Leslie. The new stairs at the bridge will remain closed however for about 3-4 weeks until the handrailing can be supplied and installed.

A completion date of mid-August is targetted at this time.